Aspire Tower
HAVER & BOECKER

Aspire Tower

HAVER and BOECKER as manufacturer facade cladding

The 318 meter high Aspire Torch Tower is the design landmark of the Asian Games 2006 in Doha, Qatar. The tower is designed to resemble a large torch, which is received with wire mesh elements supplied by HAVER & BOECKER. The façade consists of 3452 single elements with a total area of appr. 30,000 square meters.


Throughout the facade LEDs have been installed within the mesh to create user-defined effects in varying colours. IMAGICWEAVE® a combination of metal wire mesh and LED technology designed by Haver & Boecker, provides the possibility to broadcast videos on one area of the tower.


At the bottom the Aspire Tower has a diameter of appr. 70 meters. Towards the center it reduces to appr. 27 meters. The maximum diameter at the top measures around 45 meters. The construction time of the tower was just 15 months (excluding interior finishing).


The architectural brief was to create a similar transparency in each part of the tower from one viewing point. This was achieved by increasing the opening progressively from bottom to top. By using different opening sizes the transparency can be adjusted to construction conditions accounting for different viewing distances and perspectives. Even with extreme angles such as 5 degree (looking up from the bottom) the larger open area in the top part of the tower still offers transparency in the mesh. Different viewing angles let the mesh appear similarly open over the full height creating a homogenous facade.


Using the wire mesh type DOGLA-TRIO it was possible to vary the clear openings of the horizontal wires between 14 and 44 mm. The open area was incrementally increased from 72% to 85%.


The vertical wire groups of DOGLA-TRIO consist of three specially preformed wires. HAVER & BOECKER ensured, that these wire groups run in one continuous line from element to element across the full height of the tower. The standard elements are 8 meters high with a maximum width of 1,96 meters; special elements are as long as 13 meters.


Utilising the trapezoidal form for all elements, the wire mesh can clad circular buildings of varying diameters such as the Aspire Tower. The polygonal layout makes the facade appear circular without the requirement for costly panel form bending.


The mounting system was developed by HAVER & BOECKER and coordinated with the facade planners and metal contractors. At the top each mesh element is equipped with an open hook strip, which creates an L-Profile when hung on-site. The bottom part of the panel has a flat tension profile with clevis screws and pressure springs at appr. 200 mm centers, which allow for individual tensioning of each element. To reduce deflection and inherent vertical loadings, each element is connected in the center to round tubes behind the mesh using wire connectors.


HAVER & BOECKER supplied ready-to-install mesh panels direct to site, where they were tensioned into frames in a specially built manufacturing hall. As a final step, the frames were lifted to their final destination on the facade, where they were connected to the structure of the tower.


Due to the tower’s height and exposed location, extreme standards for noise emission and windloads were required. The effectiveness of wire mesh for such projects was proven by means of various tests in a wind tunnel.


HAVER & BOECKER IMAGIC WEAVE® Integration of LED-Techniques into wire mesh facades.


The combination of LED technology and woven wire mesh enables the creation of many distinct lighting effects including full video presentations. The special integration of the LED diodes into the wire mesh ensures that the visual aspects of the facade are not disrupted by interfering profiles: The homogenous appearance of the facade is maintained at all times, even when the LED’s are not in use. Additionally this type of attachment offers an easy replacement of single LED strands as required during maintenance.


An 8 meter high section of the tower below the swimming pool has been equipped with the IMAGICWEAVE® system. The LED area is separated into three high-resolution video screens of 15 m x 8 m and three fields of 35 m x 8 m with a lower resolution, where logos or advertisements can be created. The density and number of LED diodes pre-determines the resolution and quality of the video screen.


For certain mesh types existing facade or wall claddings can be retrofitted with the IMAGICWEAVE®system.


During the Asian games, three high resolution video screens are being utilised for Games Summaries, news and advertisements. Even live broadcasts are possible at all times.


With its’ many technical innovations the Aspire Tower has become a monumental building for the Region, enhancing the pride & esteem of the Gulf State of Qatar.

A milestone in Quatar

Reynaers Aluminium as Facade system

The Middle East is currently undergoing unprecedented development in the field of architecture. Reynaers has had a branch in Bahrain since 2004, and the company is therefore playing an increasingly significant role in the region. One of the highlights – in every sense of the word – is the involvement of Reynaers in the realisation of the Sport City Tower in Doha, Qatar. With its highest point 320 metres above the ground, this tower – also known as the Aspire Tower – is currently the tallest structure in the country.


The tower has a great diversity of functions, with a hotel on the lower seventeen floors, a health club with a protruding swimming pool, a conference centre, a Presidential Suite at a height of 150 metres above ground level, a sports museum at 184 metres with an observation deck, and a revolving restaurant at a height of 200 metres. The building was designed by the architect Hadi Sumaan in collaboration with Arup & Partners, Bureau Happold and MaP3. The main contractor is Midmac-Six Construct. The tower has forty thousand square metres of floor space and comprises a concrete core encased in a double skin façade designed and produced by Reynaers. For this project, the Reynaers Institute engineers carried out thorough research into the physical constructional properties of the façade of this building. The unusual streamlined form of the tower, combined with the extreme climate, demanded a careful analysis of the façade. This façade is made up of aluminium profiles, extruded in Saudi Arabia in accordance with Reynaers’ specifications, along with glass and rustproof wire mesh. Trials were carried out at the Reynaers Institute in order to test the waterproofing and windproofing of the façade, and to be able to calculate the effects of wind on the design. This façade also incorporates an advanced system of programmable artificial light.


Deadline On top of the already considerable complexity of this project came the unrelenting schedule. At the end of 2006, the tower served as the symbol of the fifteenth Asian Games, which were held in Qatar. During the Games, a ten-metre tall Olympic flame burned at the top of the tower. This event meant that the tower had to be completed before a very strict deadline, a deadline that was met with time to spare. The structure was complete eleven days before the opening ceremony of the Games, and the flame could be lit, 287 metres above the ground, sheltered from the wind by the extension of the façade up to a height of 320 metres. The project was completed in May 2007 and the building was put into use. The Olympic flame has now made way for a laser, which can be seen for miles around. The fact that the Aspire Tower was finished in time can justifiably be considered an achievement of Olympic proportions. Reynaers Aluminium was only contracted to create the façade in January 2006! By starting work at a rapid rate on the extrusion of the total of 350 tonnes of aluminium, we were able to supply the material to the Belgian firm JAP – who constructed the façade – from April onwards.


Materials The bases for the façade are the CW 50 and CW 86 façades, with a large number of speciallydesigned profiles. All aluminium profiles feature a layer of silver metallic paint in order to match the rustproof mesh. “Reynaers has delivered a total solution in its double skin façade. We designed aluminium profiles that satisfy the demands of this architecture and this project. A special solution was developed for the water drainage, which was tested extensively and which satisfies our strict standard for airproofing, waterproofing and wind resistance,” according to Frank Goudman, exports director at Reynaers Aluminium. With a wave of construction that is likely to continue for several years, the Middle East represents an important growth market for Reynaers. The company has now brought new products onto the market there, such as the Eco System and CS 86-HI, and GP 51 sliding windows made entirely of glass in aluminium frames, with no vertical struts.

Featured Projects
Latest Products
News
Nature, character, and transparency form create a harmonic balance that characterizes this latest house by the Garcés de Seta Bonet
4 Aug 2022 News
Nature, character, and transparency form create a harmonic balance that characterizes this latest house by the Garcés de Seta Bonet

Surrounded by nature and with a broad view over Catalonia's Costa Brava landscape, Garcés de... More

Les Grandes Terres reconstruction and extension project brings a sophisticated urbanity to its Paris neighbourhood
4 Aug 2022 News
Les Grandes Terres reconstruction and extension project brings a sophisticated urbanity to its Paris neighbourhood

Adding to the urbanity of a Paris neighbourhood, this project by Hesters-Oyon Architectes involves t... More

BLAF architecten experiment through their dynamic House hkZ design with the essential components of the single-family home
4 Aug 2022 News
BLAF architecten experiment through their dynamic House hkZ design with the essential components of the single-family home

Belgian practice BLAF architecten is known for exploring complex housing sustainability, affordabili... More

Sculptural, flower-shaped Holland Casino Venlo by MVSA Architects displays a colourful, interactive facade
4 Aug 2022 News
Sculptural, flower-shaped Holland Casino Venlo by MVSA Architects displays a colourful, interactive facade

Located close to the German border, Holland Casino Venlo is a flower-shaped, sculptural building by... More

Seichii Yamada & Associates reimagine the traditional Japanese house in a striking silver façade
3 Aug 2022 News
Seichii Yamada & Associates reimagine the traditional Japanese house in a striking silver façade

Located in Shizuoka city in Japan, House in Nishichiyoda designed by Seichii Yamada & Associates... More

Sigurd Larsen designs a black timber-clad cabin that resonates with Nature
3 Aug 2022 News
Sigurd Larsen designs a black timber-clad cabin that resonates with Nature

Danish Architect Sigurd Larsen designs a tiny cabin retreat in collaboration with Berlin-based hospi... More

Making infrastructure do more: MVRDV and StudioPOD complete One Green Mile in Mumbai
3 Aug 2022 News
Making infrastructure do more: MVRDV and StudioPOD complete One Green Mile in Mumbai

Recently completed in Mumbai, the One Green Mile project by MVRD and StudioPOD transforms a series o... More

John McAslan + Partners take a ‘Fabric First’ approach to the renovation and enhancement of Glasgow’s celebrated Burrell Collection building
3 Aug 2022 News
John McAslan + Partners take a ‘Fabric First’ approach to the renovation and enhancement of Glasgow’s celebrated Burrell Collection building

Glasgow’s Burrell Collection includes 9,000 works of fine and decorative arts spanning 600 yea... More